IDSE Implementation Timeline

Schedule for systems in a combined distribution system (CDS) is based on that of the largest system in the combined distribution system

Sch. Systems Serving:

Submit 40/30 Certification, SM, SSS Plan, or receive VSS Waiver by:

Complete SM or SSS By:

Submit IDSE Report (only systems conducting SM or SSS) by:

1

>100,000

Oct. 1, 2006

Sept. 30, 2008

Jan. 1, 2009
2

50,000–99,999

Apr. 1, 2007 Mar. 31, 2009 July 1, 2009
3 10,000–49,999 Oct. 1, 2007

Sept. 30, 2009

Jan. 1, 2010
4

< 10,000

Apr. 1, 2008 Mar. 31, 2010 July 1, 2010

Getting Started

IDSE Presentation (3.5 MB)

Stage 2 DBPR Rule (external link)

Final IDSE Guidance (2.8 MB)

Stage 2 DBPR Fact Sheet

EPA's Stage 2 Web Page (external link)

Water System Schedules (This lists each water system and the schedule they are assigned)

Your Water System's Monitoring Period

Once you know which schedule your system is assigned, download the appropriate files.

Schedule Timeline Monitoring Period
1 Sch. 1 Timeline Sch. 1 Monitoring Period
2 Sch. 2 Timeline Sch. 2 Monitoring Period
3 Sch. 3 Timeline Sch. 3 Monitoring Period
4 Sch. 4 Timeline Sch. 4 Monitoring Period

Additional Information

40/30 Certification Form

Protocol for Recommending Stage 2 DBPR compliance monitoring sites

 

To view and print the PDF documents on this site, the FREE Adobe Acrobat Reader is required. Click on the Adobe logo below to download it.

Get Acrobat Reader


Georgia Environmental Protection Division
Georgia Department of Natural Resources
2 Martin Luther King Jr. Drive, Suite 1152 East Tower
Atlanta, GA 30334
Telephone: 404.657.5947 or 888.373.5947 (toll-free throughout Georgia)
Copyright © 2008 by the Georgia Environmental Protection Division. All rights reserved.